The construction work for the dfskyway™ was distributed between two locations, − one was the site of the actual road construction and the other was the Casting Yard at Mirzapur, Haryana - the location of the batching plant and concrete segments casting.

The Badarpur Team was required to erect the spans by precast segments with the specific nomenclature given to them. A total 2164 units of precast segment casting were completed in just 407 days. The activity was accomplished 2.5 months ahead of planned baseline schedule. The whole activity is encompassed of Main carriage way, and merging spans with seven different types of segments.